How to generate S-curve for physical progress where work consist of different units
Dear Sir/Mam
Am working in a sewerage project, I want to generate a S-curve for physical Progress
Problem I am facing for S-curve:
We have different unit of work, like Sewer line, pipe laying and house sewer connection in meter, manhole chambers, and inspection chambers and pump stations in numbers. And WBS of my construction schedule is based on the areas (divide based on different areas of the city)
By using MS project or Oracle Primavera is it possible to generate a physical progress curve which represents the entire project. If yes kindly help.