Work progress at status date
Hello Planners and MSP specialists,
How could it be possible to make MS Project compute the percentage between actual work and theoritical work at the status date?
One 5 day task starting Monday
Two resources assigned to this task: R1 is working 10 hours / day; R2 is working 8 hours / day
Status date is Wednesday night
R1 has worked 10 hours on Monday, 9 on Tuesday, 8 on Wednesday, or 27 hours
R2 has worked 5 hours on Monday, 4 on Tuesday, 3 on Wednesday, or 12 hours