WorleyParsons Planner
Planner for BHP Billiton Olympic Dam Expansion Projects under Worley Parsons Supervision.
WorleyParsons
Planner for BHP Billiton Olympic Dam Expansion Projects under Worley Parsons Supervision.
Responsibilities include Planning, Scheduling, Monitoring and Control of Oil & Gas and Infrastructure projects. Approved by Occidental Petroleum as Sr. Planning Engineer for their EMC Projects.
Project 3
Owner : New Doha International Airport
Industry : Infrastructure
Project : Utilities Package for New International Airport in Doha
Client Monthly Progress Report, Weekly Progress Trending, Scheduling Analysis, Project control related correspondence and variation & claims input, monthly contractors billings recommendation.
Lead Planner for a nine person (peak) planning team on the detail design and procurement phase for a large new build gas platform
As a Lead Project Engineer (functionally Project Manager) I am involved in management of multi-million Oil & Gas Engineering, Procurement and Construction Projects from Front End Design to Project financial Close-out within schedule & cost to an acceptable quality, as a Single Point Responsibility. Key tasks are:-
1. Manage and coordinate multidiscipline engineering activities to ensure projects are executed in a safe, efficient, cost effective and timely manner.
Started as a Trainee Planner with WorleyParsons in 2006.
Assissted in Maintaining Master Schedules for:
Stage 5A & Stage 5B Dampier to Bunbury Natural Gas Pipeline.
Neerabup Facilities & Pipeline Project.
Mandurah Lateral Project.
Rio Tinto Expansion Projects (Electrical Upgrade, Security & Compliance Upgrade)
Weld Range Iron Project
Roy Hill Iron Ore Project.