Siemens

Siemens

Construction Project Planner, Siemens, London Healthrow Airport Baggage Handling System

START Date

Project Planner

Siemens Terminal 1 & Terminal 2 Projects, Heathrow Airport

  • Constructed integrated programmes, using Oracle Primavera 8.2 (P6), to reflect full scope of delivery for multiple projects, i.e.

Chinyere Muoka

First Name
Chinyere
Last Name
Muoka
Professional Since
Years Experience
0
Telephone Number
07530709639

I have vast experience in the following areas, Primavera P3e Resource and Cost Analysis, Primavera P3e Managing Project Data, Primavera P3e Reports and Graphics, Primavera P3e Planning and Scheduling, Solid Hands-On Experience with Microsoft Project. Excellent Knowledge of PRINCE 2 version 4 methodology. Project life Cycle –Configuration Management and Change Management. Risk Assessment & Issue Analysis

Xenia Marami

First Name
Xenia
Last Name
Marami
Professional Since
Oldest experience
Years Experience
44
Telephone Number
0097433470660
LinkedIn Profile
pmarami

TECHNICAL SKILLS   

·        MS office expert

·        MS Visio 2007

·        MS project 2007

Senior Project Engineer / Contract Engineer, SIEMENS, New DOha international airport

START Date

Having completed an extensive cycle in higher education and Physics, I moved to industry in June 2004 as a software consultant. Since then I have primarily worked on security systems and special applications. I have been employed in several high end projects in Qatar, in various roles, such as special applications consultant, software analyst, project coordinator, duties’ administrator, Quality Control (QC) -tester and customer trainer.

Martin Hofmann

First Name
Martin
Last Name
Hofmann
Professional Since
Oldest experience
Years Experience
2
Telephone Number
+436602539500

P6, P3.1, MS-Project, MS Office, MS Access, ACAD 2002/2005/2010, Solid Works, SAP Office

Project Planner, Siemens, Germany, Heat Recovery Boiler - Lausward

START Date

-  Inquiry the progress and monitoring the schedule with responsible shareholder

-  S-curves for the actual progress

-  Identify, analyse and evaluate critical activities (critical path analysis, baseline variations)

-  regularly reporting to the project leader and the customer

-  Induction and tracking the actual hours(on role basis) for the ressource-planing

Heath Annan

H
Heath Annan 👤 Member for 23 years 4 months
First Name
Heath
Last Name
Annan
Professional Since
Oldest experience
Years Experience
13
Telephone Number
07708 411332

In no particular order:

Junior Planner, Siemens, Electricity Alliance North (NG) Projects

R
Rob McGowan 👤 Member for 13 years 6 months
START Date

Progressing and Updating

Monthly Reporting on milestone for diffrent stages of projects

Reporting on EVM, SPI, and CPI

Create Resource Loading tables

Reporting on Quality

Using SAP to report on hours assigned to projects and the hours resources have been booked to