QA/ QC Electrical Engineer (Low Current), Saudi Oger Ltd., King Abdullah project for Development of security compounds – Kap1 –Ministry of Interior - ($2019

J
Joel Luna 👤 Member for 11 years 6 months
START Date
Experience Hours (Planning & Scheduling)
4500

*  Conduct site survey prior to design execution to assist engineering department in case of any modifications and/ or extensions.

*  Review and implement designs in conformance with specifications and standards (ISO, NFPA, BICSI) and analyze soundness of the design scope.

*  Following up approval of execution drawings and material submittal sheets prior to any electrical works.

QA/ QC Electrical Engineer (Low Current), Saudi Oger Ltd., King Abdullah project for Development of security compounds – Kap1 –Ministry of Interior - ($2019

J
Joel Luna 👤 Member for 11 years 6 months
START Date
Experience Hours (Planning & Scheduling)
4500

*  Conduct site survey prior to design execution to assist engineering department in case of any modifications and/ or extensions.

*  Review and implement designs in conformance with specifications and standards (ISO, NFPA, BICSI) and analyze soundness of the design scope.

*  Following up approval of execution drawings and material submittal sheets prior to any electrical works.

Marcelo Cobrador

First Name
Marcelo
Last Name
Cobrador
Professional Since
Oldest experience
Years Experience
0
Telephone Number
+ 966537514801
LinkedIn Profile
Marcelo Cobrador
Facebook Profile
Marcelo Cobrador

Project Controls Manager, Saudi Oger Ltd., King Abdullah Project for the Development of Security Centers – Phase 1 (KAP1)

START Date
END Date

Project: King Abdullah Project for the Development of Security Centers – Phase 1 (305 sites) – KAP1.

Location: Riyadh, Saudi Arabia.

Value: US$ 2 Billion.

Client: Ministry Of Interior (MOI)

Team Composition: 22 (2 Section Planning Managers) + 6 Senior Schedulers + 12 Schedulers + 2 Reporting Engineers).

Prject Controls Manager, Saudi Oger Ltd., Rehabilitation, Expansion, Operation, Development, and Maintenance of Prince Mohamed Bin Abdulaziz International Airport, Madinah

START Date
END Date

Project: Rehabilitation, Expansion, Operation, Development, and Maintenance of Prince Mohamed Bin Abdulaziz International Airport.

A joint venture project (Saudi Oger Ltd., TAV, ACC)

Location: Madinah Munawwarah, Saudi Arabia.

Value: US$ 1.2 Billion.

Client: General Authority of Civil Aviation (GACA)

Team Composition:7 (1 Senior Scheduler + 2 Schedulers + 2 Reporting Engineers + 2

Project Controls Manager, Saudi Oger Ltd., King Abdullah WAGF Project Package 2

START Date
END Date

Project: King Abdullah WAGF Project Package 2, Construction of 5 hotels.

Location: Madinah Munawwarah, Saudi Arabia.

Value: US$ 560 Million.

Client: King Abdullah WAGF

Consultant: Omrania & Associates

Team Composition: 7 (2 Senior Planning Engineers + 5 Planning/PCS Engineers).

Planning Manager, Saudi Oger Ltd., Princess Nora Bint Abdulrahman University For Women PNU – Package 1

START Date
END Date

Project: Princess Nora Bint Abdulrahman University For Women PNU – Package 1. Project components are 19 academic and administrative buildings, a hospital, 400 staff villas, 3 mosques, a clock tower, 5 gates, and 10 security buildings and guard houses. Total build-up areas is 1 million m².

Value: US$ 3 Billion.

Location: Riyadh, Saudi Arabia.

Client: Ministry of Higher Education and Ministry of Finance

Project Controls manager, Saudi Oger Ltd., Jabal Omar Development Project JODP

START Date
END Date

Project: Jabal Omar Development Project JODP. Project components are 15 hotel and seasonal residential towers including podiums, 13,600 m² mussallah building, and external works). Total build-up areas is 1,260,000 m².

Value: US$ 2.9 Billion.

Location: Makkah, Saudi Arabia.

Client: Jabal Omar Development Company

Team Composition:11 (5 Senior Planning Engineers + 6 Planning and Project Controls

PLANNING ENGINEER, Saudi Oger Ltd., King Abdullah Project for Development of Security Centers (KAP-1)

START Date
END Date
Experience Hours (Planning & Scheduling)
750
Experience Hours (Cost Management)
250
Experience Hours (Forensic Analysis)
50

1.Contract documents study.

2.Detailed Time Schedule.

3.Resources & Cost loading.

4.Updating, Monitoring & Controlling.

5.Progress reports.

6.Tracking issues.

7.Recovery Schedule.

8.Sites coordination for civil works.

9.Monitoring S/C's productivity on sites.

PLANNING ENGINEER, Saudi Oger Ltd., Saudi Arabia National Guards Housing Project

START Date
END Date
Experience Hours (Planning & Scheduling)
1050

1.Contract documents study.

2.Detailed Time Schedule.

3.Resources & Cost loading.

4.Progressive elaboration throughout different project stages.

5.Updating, Monitoring & Controlling.

6.Progress reports.

7.Tracking issues.

8.Preparation of Claims & V.O.'s.

9.Recovery Schedule.

10.Site coordination for civil works.

11.Monitoring material usage for restrict controlling