Reliance Industries Limited
Barada Biswal
Project Management
Strategic Planning
Project control Manager, Reliance Industries Limited, J3 Reliance
Senior Manager Project control:
- Team handling
- Mupltiple projects managed
- Project handeled: Refinery Off Gas Cracker, MEG, LDPE, LLDPE, PTA,PET
- Developed and maintain schedule in P6
- Critical path, delay analysis and EVM analysis
- Change Management
- Budget control and budget monitoring
- Variance analysis
- Automation in cost reporting and progress reporting system
- Database and cost bechmarking
- Cost estimation (class 3,4)
- ASPEN tech cost evaluation
MAINTENANCE MANAGER, Reliance Industries Limited, ROGC
o Monitoring and maintaining rotating equipment like Cryo centrifu
VIRALKUMAR PATEL
ANALYST / PLANNING ENGINEER, Reliance Industries Limited, Offshore and onshore oil and gas projects
Worked as planning Engineer. responsible for Project Schedule, Schedule update and MIS Reporting for Onshore,Offshoe,Projects,CBM Projects, offshore drilling schedules.
Vikash Kumar
sital mukherjee
Planning Engineer
Construction Project Planner / Senior Planner, Reliance Industries Limited, Network Operation Centre
PRIMARY DUTIES AND RESPONSIBILITIES:
•Plan and schedule the project by developing a project master schedule in line with the proposal requirements through the application of the primavera P6 software.
•Identify the project deliverables, milestones, and required tasks and targets to determine the staffing requirements, and allotment of available resources to various phases of the project through the project measurement system.
Construction Project Planner / Senior Planner, Reliance Industries Limited, Network Operation Centre
PRIMARY DUTIES AND RESPONSIBILITIES:
•Plan and schedule the project by developing a project master schedule in line with the proposal requirements through the application of the primavera P6 software.