Mouchel Parkman

Mouchel Parkman

Senior Planning Engineer, Mouchel Parkman, Jubilee Line Signals Upgrade

START Date
END Date

Key Responsibility Areas:

 

  • Develop the 16-week Rolling Programme at Level 4

 

  • Develop the 5-week Rolling Programme (Work Plan Level 5)

 

  • Provide inputs to the weekly progress report and 4-weekly Period Progress Review Report, including current performance indicators and analysis derived from quantified progress / actual labour hours / actual costs inputted on to the PMP, identifying any significant schedule and costs variances to be explained / further investigated.  Also report on the stat

Senior Tender Planning Engineer – Civils, Mouchel Parkman, Varied

START Date
END Date

Reporting to the Chief Estimator. Duties included:

  • Preparation of detail tender programmes covering design, installation, test and post commissioning works. Early identification of external factors such as road closures and third party interventions/ approvals ( e.g. Local authority consents for road closures).
  • Production of Key Tender supporting deliverables such as resource loadings for installation gangs.
  • Analysis of key factors affecting operational efficiency such as red zone working restrictions and available rules of route.