Mansell Construction

Mansell Construction

Design & Planning Manager, Mansell Construction, All Regional Projects

START Date
END Date
Experience Hours (Planning & Scheduling)
5000
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
1000

Design & Planning Manager for all regional projects. Responsible for all tender and contract planning as well as design coordination on live D&B contracts

Planning Manager, JLP, Mansell Construction, Balfour Beatty, Verry Construction, Various

START Date
END Date
  • Advanced understanding of various forms of tender documents, contract documents and specifications.
  • Advanced understanding of various methods of planning, programming and progress monitoring.
  • Advanced understanding of risk and opportunity management with particular reference to planning/programming.
  • Advanced understanding of the construction market, methods of construction, plant, equipment and labour requirements.

Construction Project Planner / Senior Planner / Forensic Analyst, Mansell Construction, LPIs

START Date
END Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
2500
Experience Hours (Forensic Analysis)
2500

I am responsible for all the Project and Tender programme within the Gatwick Airport Team, of whom we only have one client, Gatwick Airport Limited.  I produce and report and progress various projects on regular basis.  In addition, I attend client / sub contractors meetings to ensure that all changes are captured.  Because all works within the team are surrounding a live / operating airport, robust planning is required to ensure the integrity of airport operations, security, safety and passenger experience is maintained.  Two senior planners are currently working under