project manager, SPIC Yuanda Environmental Protection Engineering Co.,Ltd., Xinchang 2×700MW unit ultra-low emission retrofit project
Xinchang 2×700MW unit ultra-low emission retrofit project
Xinchang 2×700MW unit ultra-low emission retrofit project
Yanshan Lake 2×660MW Unit Denitration Modification Project
Yanshan Lake 2×660MW Unit Denitration Modification Project
project name:Changshu 2×300MW Unit Desulfurization Reform Project
Served as a full-time electrical post in the project, and began to contact the project manager's daily work of various conversions, and successfully completed 168 trials of Changshu 2×300MW units (including economizer transformation, air preheater transformation, and induction and increase integration transformation). Transported the project and successfully passed the environmental protection acceptance
project name:Changshu 2×300MW Unit Desulfurization Reform Project
Served as a full-time electrical post in the project, and began to contact the project manager's daily work of various conversions, and successfully completed 168 trials of Changshu 2×300MW units (including economizer transformation, air preheater transformation, and induction and increase integration transformation). Transported the project and successfully passed the environmental protection acceptance
project name:Changshu 2×300MW Unit Desulfurization Reform Project
Served as a full-time electrical post in the project, and began to contact the project manager's daily work of various conversions, and successfully completed 168 trials of Changshu 2×300MW units (including economizer transformation, air preheater transformation, and induction and increase integration transformation). Transported the project and successfully passed the environmental protection acceptance
project name:Changshu 2×300MW Unit Desulfurization Reform Project
Served as a full-time electrical post in the project, and began to contact the project manager's daily work of various conversions, and successfully completed 168 trials of Changshu 2×300MW units (including economizer transformation, air preheater transformation, and induction and increase integration transformation). Transported the project and successfully passed the environmental protection acceptance
Main responsibilities:(1) Development and management of level 3 schedule in the EPC project;(2) Development and management of schedule database for the project;(3) Development and management of schedule management system in the project;Achievements:(1) Having developed and managed the master schedule for project with debugging 50 days in advance;(2) Having Been familiar with cons
Main responsibilities:(1) Being responsible for development and management of plan and cost in the company's infrastructure projects;Achievements:(1) To ensure that the scope of schedule and cost are under control for the company infrastructure project;(2) Establishing standardized infrastructure project management system;
Refer to Senior Contract Administrator Senior Planning Engineer position in the Profile page.