Leighton Australia Planner

3 month contract to tidy up hacked P6 programme with too many inexperienced users and rudderless contract planners.

Programme was fully resourced, using timesheets, and their primary actuals and forecasting repository & tool.

Required some detailed analysis into data, and many hours of correcting erroneous data, cost plugs then aligning of P6 cost values with the G/L and excel based Cost Analysis Report.

Baseline also needed to be updated to to bring it into alignment, along with the correction of the Stored Period data.