planning and project control manager, isi, (1)Renovation and Reconstruction of Foroozan Offshore Complex, Engineering Project, Khark Island

START Date
  • Preparing the baseline plan for the project & update the schedule.
  • Continuous relation with site and going on required missions.
  • Preparing Work Breakdown Structure.
  • Preparing Master Document List and Register.
  • Preparing daily, weekly and monthly reports.
  • Preparing Monthly Financial Invoices.
  • Preparing Change order reports.
  • Preparing management and any other required reports.
  • Preparing forecast activities for the coming month.
  • Making database for correspondence and follow up.
  • Coordi