Dennis Hanks
Currently focusing on Schedule Risk Analysis with the intent to develop variable cost and schedule duration contingencies. This usually requires a schedule evaluation to determine fitness-for-use.
Intercede
Currently focusing on Schedule Risk Analysis with the intent to develop variable cost and schedule duration contingencies. This usually requires a schedule evaluation to determine fitness-for-use.
1998 - 2006 Intercede Houston, TX
Consultant
Advised multi-national construction joint-venture on project controls techniques and procedures for three project sites – one domestic and two foreign (Jamaica and Surinam).
Commercial Manager on a 3 station natural gas compression project in Bolivia. Challenge was the integration of a Canadian engineer with a Bolivian contractor under US management and working with an uncooperative South American owner.
2007 - Present Intercede Houston, TX
Consultant
Two phase effort regarding an LNG gasifier and pipeline. Primarily schedule risk assessment utilizing data from un-sophisticated sub-contractors. Software used - Pertmaster 8.53 and Primavera 6.7.
Schedule risk analysis for a pipeline replacement program. Multi-project effort entailed re-casting one project schedule and developing basic metrics, validating existing systems and suggesting improvements for the other projects.