Foster Wheeler Energy UK Project Controls Engineer
Project Controls Lead
• GASCO (Abu Dhabi Gas Industries); Habshan-5 Project; ($94 million Scope); UAE.
Foster Wheeler Energy UK
Project Controls Lead
• GASCO (Abu Dhabi Gas Industries); Habshan-5 Project; ($94 million Scope); UAE.
EXPERIENCE (Summary):
Contracts Planning Engineer
• Indian Oil Company (IOCL); Paradip Refinery; ($ 4 billion Scope); India.
Senior Planning Engineer assisting in setting up and monitoring the Front End Engineering for a major refinery in NW India for IOCL. The FEL started in Dec 06 and was completed in March 2008. I was responsible for assisting in setting up the Level 3 Schedule using Primavera P5 & monitoring the Progress of the project. Milestones & DMS were also used to monitor progress of the documentation.
Senior Planning Engineer working within the Offsite & Utilities Team for the Detail Design of IOCL Paradip Refinery. Having developed the Level 2 schedules within Milestones and expanded them to form the Level 3 schedules on Primavera P6 These were updated monthly to determine the status of the project. Overall progress was calculated through the Drawing & Document Control Package.
I then developed the Level 3 Construction Schedule for the Offsites & Utilities which was passed to the Indian Office for further detailing.
Lead Planning Engineer working on the FEED for South Pars Development Phs 6, 7 & 8. Responsible to the Project Controls Manager for the production of weekly progress and input to the monthly reports. Working Closely with Instrument & Telecoms Design Engineers for input to Schedule. Using Primavera P3