Delay Analyst, Confidential, Undisclosed Confidential Projects

START Date
END Date

 

Identification of claims for delay and/ or disruption on the Bucharest to Constanta rail project

Utilisation of time slice analysis to identify causes of critical delay to a rail rehabilitation project

TILOS software

Contract administration of notices

FIDIC Red Book – contract values up to €150 million

Delay Analyst, Confidential, Undisclosed Confidential Projects

START Date
END Date

 

Drafting of claim documents for two separate Contracts on the Bucharest to Constanta rail project

Claim 1 for an extension to the reasonable Time for completion date previously awarded by the DAB

Claim 2 for an extension of time to July 2013 using timeslice methodology to show delay impact to critical path

FIDIC Red Book – contract values up to €150 million

Report on Planning Controls, Confidential, Cross Rail

START Date
END Date

 

Preparation of period programme report for Crossrail Joint Venture company

Identification of programme delay events and slippages across progress periods

Carrying out programme control checks on P6 programmes

Identifying weaknesses in JV’s strategy for delay recovery

NEC Contract