Project Controller, Atkins, Transportation

START Date
END Date
Experience Hours (Planning & Scheduling)
3350
Experience Hours (Cost Management)
3600
Experience Hours (Forensic Analysis)
350

PROJECT CONTROLLER 

  • Undertook effective project cost analysis
  • Produced project plans detailing programmes of works with clearly defined milestone dates for all project activities.
  • Ensured projects are being carried out to agreed contract specifications, in accordance with best practice, and within budget/time constraints.
  • Effectively reporting on project performance against client KPIs and organisation’s performance targets.
  • Developed cash/cost flow project reports.

Anthony Obasi

First Name
Anthony
Last Name
Obasi
Professional Since
Oldest experience
Years Experience
5

Project control and planning professional in the UK tranportation industry

Planning Manager, Atkins, Barrow Strategic Redevelopment

C
Craig Lea 👤 Member for 7 years 9 months
START Date
END Date
Experience Hours (Planning & Scheduling)
4500

Atkins May 2014 – May 2016 PLANNING MANAGER (D&E / Major Projects)

• Heading up the Planning and Project Control functions for ‘BSRP’ – Barrow Strategic Redevelopment Programme, £350M Capital Investment.

Mohsen Alaali

First Name
Mohsen
Last Name
Alaali
Professional Since
Oldest experience
Years Experience
4
LinkedIn Profile
https://www.linkedin.com/in/mohsenalaali

Project Coordinator/Assistant Project Manager, Atkins, Multiple

START Date
END Date
  • Project Management: Mohsen is involved in financial planning, quality control, QA processes, coordination of engineering and planning input and business development. He continues to provide project management systems specialist support as well as project management (technical and commercial) of design and site operations activities of multidisciplinary projects including Infrastructure, Utilities, Mix Use and Residential Buildings, and Industrial Schemes.

assessment engineer/project manager, Atkins, SSL and BCV london underground PPP contract

START Date
END Date
Experience Hours (Planning & Scheduling)
50

Metronet – Assessment Engineer/Assistant Project Manager

Metronet were a PPP provider to London Underground for the upgrade and maintenance of the Sub-Surface lines, and Bakerloo, Central and Victoria Lines. Ben was seconded to Atkins, one of the Metronet partners, to assist their pumps and drainage team.