Executive - Planning, AMR Constructions Ltd, Rajiv Swagruha housing Development Project

START Date
END Date

 

a.     With Microsoft project planning and scheduling software, defined and sequence its activities, estimated its resources, estimated the activities durations and finally developed the Master Program of Work as the project baseline schedule which was continually monitored and updated during the project’s progress.