Projects Worked on:

Turnkey projects (SIX Numbers) for 220/132/33/22/11 kV Substations at Abu Dhabi, Ras AL Khaimah, Delma Island & Al Ain.

Civil:          Design and Construction of Substation Building
Electrical:     Design, Procurement, Erection, Testing and Commissioning of all electrical equipments
Mechanical:     Design, Procurement, Erection, Testing and Commissioning of HVAC and fire protection system.

PLANNING ENGINEER, ETA - PPD, Power Substations

START Date

Current Role

  • Preparation and Monitoring of Master Programmes for various substation projects.
  • Cost loading and resource loading of the Construction Master Programme and monitoring the same.
  • Preparing Monthly Billing graphs for tracking, monitoring and controlling the cash flow of the project.
  • Tracking and control of the idle manpower and machinery cost incurred due to delay in the project.
  • Preparing weekly and monthly reports for tracking, monitoring and reporting the overall progress of the project to the Client.
  • Conducting p