Dodsal Engineering & Construction Pte Ltd.
Dodsal Engineering & Construction Pte Ltd.
Dodsal Engineering & Construction Pte Ltd. Project Controls Engineer
Project I - Melut Basin Oil development Project Republic of Sudan EPCC of 32” Export pipeline USD 46 Million$ - Petrodar Operating Company Ltd - Republic of Sudan
• Project involves EPCC for Segment B-2 / 32” 203Km Crude Oil Pipeline originating from Pump Station-06 Musmaar to Port Sudan Marine terminal and installation of Block Valve Stations, Pumping Facilities, Pigging facilities & Permanent Cathodic Protection.
Project II - Abu Dhabi Polymers Company Limited-ADNOC (Borouge PE Plant - Step II Project) - UAE
• Project involves EPCC for Segment B-2 / 32” 203Km Crude Oil Pipeline originating from Pump Station-06 Musmaar to Port Sudan Marine terminal and installation of Block Valve Stations, Pumping Facilities, Pigging facilities & Permanent Cathodic Protection.
Project II - Abu Dhabi Polymers Company Limited-ADNOC (Borouge PE Plant - Step II Project) - UAE
Sr. Engineer - Project Planning and Control, Dodsal Engineering & Construction Pte Ltd., EPC TRANSCO Pipeline Project
START Date
END Date
Experience Hours (Planning & Scheduling)
3550
Experience Hours (Cost Management)
450
Experience Hours (Forensic Analysis)
700
· Developing detailed project schedules with cost loading and ensure consistency with contract documents (Conditions of Contract, Specifications, Bill of Quantities, Drawings, …)
· Identifying the major milestones, critical approvals and long lead procurement items
· Analysing gaps between the planned and actual progress and highlight the areas of concerns which required action of the associate task member.