Kier Construction

Kier Construction

Kier Construction Senior Planner

The scheme involved the construction of a £400M modern, compact and efficient 885 Megawatt Combined Cycle Gas Turbine power station with high quality contemporary industrial architectural design. The contract was based upon NEC 3 option D with a Target cost with Bill of Quantities.

Civil Scheduler, Kier Construction, Channel Tunnel Rail Link (C320)

START Date
END Date
Experience Hours (Planning & Scheduling)
3800
Experience Hours (Forensic Analysis)
1100

Channel Tunnel Rail Link, Contract 303, Dagenham. Value £23 million. Construction of 3 new road bridges over the live railway and the diversion of a river beneath the railway. Responsible for medium and long term construction planning, possession planning, production of reports including earned value measurement and determining the effect of change on the project. Planning support for bid preparation.