Chiyoda Technip Joint Venture (CTJV)

Chiyoda Technip Joint Venture (CTJV)

Schedule Engineer, Chiyoda Technip Joint Venture (CTJV), Al Khaleej Gas Phase 2, Ras Laffan

START Date
END Date
Experience Hours (Planning & Scheduling)
4800
Experience Hours (Forensic Analysis)
450

-prepare PMC (pre mechanical check)

-update master construction schedule of Level-III based on the information from supervisor by use of Primavera (P3 /3.1).

-define linkage between construction schedule and commissioning schedule

-CPM analysis using master construction schedule of Level-III

-check subcontractor’s detail construction schedule of Level-IV based on the Level-III schedule.

-review 3 weeks look-ahead schedule submitted by subcontractors.

-loading of man-power and/or progress weighted value to activities on Level-III schedule.