2 Milestones each Schedule must have

Member for

21 years 8 months

Mike,



It seems like some scheduling experts agree with you on the issue of constraints.



_ “Assigned constraints: Overrides computer calculations at the core of CPM scheduling.

Result: According to one scheduling expert, "If you do this, it’s a bar chart" and not a traditional CPM network diagram and schedule.”



From:



http://www.pmicos.org/fse.asp



Richard,



A schedule without driving logic is a Bar Chart.



Project Managers are to verify schedule logic, is their responsibility, they should schedule the way they want to build the thing as long as it is reasonable. If your PMs have to override their own logic very frequently I would call it bad planning, bad scheduling, bad team work, well maybe just Bar Charting.



Sorry I did not answered before but I am not getting e-mails from PP.



Best regards,

Rafael

Member for

18 years 7 months

Mike



All software has millstones - mosstly it is the way the programme deals with forward and backward passes! At the moment it appears that Powerproject has the fewest millstones



I don’t know how we put in the Irtish foreman’s milestone - "If I was building it I wouldn’t start from here"



Rafael



What the hell does logic have to do with making a schedule? I don’t know many Project Managers that have ever allowed logic get in the way of the way they want to build something!

Member for

21 years 8 months

Unfortunately as Mike said there is no software that can handle well intermediate milestones without breaking the rules of logic every time you use them. Same goes for logic relationships other than FS, and also for negative lag.



If you schedule using forward pass and then backward pass to get late dates then everything should be driven in a forward direction. If you schedule using first backward pass and then forward pass as to determine a target project start date everything should be driven in the other direction. Milestones shall represent an added activity to the left or to the right depending on which direction you start.



There is no reason why PDM shall break the rules of logic.

Member for

17 years 3 months

Dear Rafael,



Great Answer... haha.



The Practice Standard for Scheduling, section 2.1 Schedule Development Process Overview, page 6:



" The Schedule model must include at least two milestones; project start and project finish."



With kind regards,



Samer

Member for

19 years 10 months

Hi Rafael



Thanks for the best laugh of the week.



I am waiting for a realistic software packaage that has millstones.



Very best regards



Mike T.