TILOS Member for 14 years 4 months Member for 14 years 4 months Submitted by **@t***** on Thu, 2013-09-19 09:35 Permalink Alexandre, by default TILOS Alexandre, by default TILOS spreads the cost allocation on the duration of the task. For your need you may - create a milestone for each of the corresponding tasks - assign Start-Start-Links to locate the Milesones at the beginning of the task - assign the cost to the milestone - you may also switch off the display of those milestones with layers or filter regards Thorsten Log in or register to post comments
Member for 14 years 4 months Member for 14 years 4 months Submitted by **@t***** on Thu, 2013-09-19 09:35 Permalink Alexandre, by default TILOS Alexandre, by default TILOS spreads the cost allocation on the duration of the task. For your need you may - create a milestone for each of the corresponding tasks - assign Start-Start-Links to locate the Milesones at the beginning of the task - assign the cost to the milestone - you may also switch off the display of those milestones with layers or filter regards Thorsten
Member for
14 years 4 monthsAlexandre, by default TILOS
Alexandre,
by default TILOS spreads the cost allocation on the duration of the task.
For your need you may
- create a milestone for each of the corresponding tasks
- assign Start-Start-Links to locate the Milesones at the beginning of the task
- assign the cost to the milestone
- you may also switch off the display of those milestones with layers or filter
regards
Thorsten