Tilos for claims on Linear projects

Member for

15 years 9 months

Thanks Mike,



I will try the email again. I deleted your last email about where I am from by accident. Apologies.



Things are very busy but the Irish economy is sluggish. However, the work and market is out there so we have to be inventive to get results. As they say, you can’t beat a good crisis and have to make the most out of it.



Regards



Matthew Edwards

Member for

19 years 10 months

Hi Matthew



This was a recent answer from PP admin regarding the links page:



"Hello All,



Please be advised that it is FREE to advertise a company and / or something relevant to planning on the Links page.



If anyone wishes to place something onto the Links page, simply send the PP Admin team your requested link, its description (to be shown next to the link on the links page) and a contact email / name etc and one of the team will get it posted on there.



Regards."



Best regards



Mike Testro

Member for

15 years 9 months

Hi Mike



Yeah, I have looked into baselining and imapcting a Time Chainage proigramme with a former colleague who is a wizard at Tilos 6.



It appears that it does an As-Planned impacted demonstration very well.



Regards



Matthew Edwards - PS Email ID removed. I have just emailed helpdesk@planningplanet.com - It appears that it is not working correctly. I would like to put my company on the links page. Do you know of any other contact e,mails. Thanks, Matthew.

Member for

19 years 10 months

Hi Matthew



It depends on what software was used during the project.



Transferring an EoT claim to a different software is always problematic.



Best regards



Mike Testro





PS

I have just noticed taht you have your email as part of your title - please be warned that there are spammers operating within PP - I would suggest you remove it.