Import problem Primavera Risk Analysis mpp file

Member for

18 years 11 months

Thanks!

Member for

7 years

Tom, 

I tried to import an mpp from Project 2013.

Regards,

Martijn

Member for

18 years 11 months

Martijn,

Thanks very much for sharing the solution!  Microsoft's proliferation of language packs has complicated a lot of things, and I would not expect PRA (rather long in the tooth) to have easily handled the complications.  Just to clarify, what was the format of the MSP file you were attempting to import?  mpp? (what year?) mpx? xml? (what year?)

tom

Member for

7 years

Thanks for the suggestion, but the problem seem to be solved.

It has to do with the language settings in MS Project. This need to be in English and not in Dutch (in my case).

Member for

19 years 11 months

Martijn, without seeng it, hard to say. If you want a quick answer to this, send me the MSP file and I will run the xml import to my P6. my address: trevorATperfect projectDOTcomDOTau