Firstly, PRA is OLD, you should seriosuly look into some of the newer SRA tools out there.

 

But one workaround to your dilema - Filters are only applied to tasks, not to links. Show the "Preceding Tasks" and Suceeding Tasks" Columns. Remove any Grouping/organisation and then sort by each of the columns to see which tasks are null in each column.

 

Member for

21 years 8 months

If there is no such pre-defined filter in your software then with the use of UDF (User Defined Field) a few formulas, a few simple filters and a script to automate execution you should be able to create the filter.

In the following video you will see the use of a pre-defined filter as well as the use of a script.  After the script is defined all it requires is to run it with a few mouse clicks, easier and faster than using Excel.

Pre-defined dangling logic filters are a better option anyone can use.

Predefined_Filters

Good Luck

Member for

21 years 8 months

When creating your filters please be reminded that it is possible for activities to have both predecessors and successors yet still suffer from dangling – hence inadequate – schedule logic. These cases – generally categorized as dangling finish and dangling start – are also known as “orphan relationships.”

Dangling01



Dangling02

 

In such case it is possible the schedule reports miss to highlight the dangling finish/start. 

Member for

22 years 9 months

Hello Scott,

I cannot find such a filter in PRA; the best way I can find to retrieve all the open activities is to insert the Preceding tasks and Succeding tasks columns in a view, then to sort the view on these fields

I hope it will help

Alexandre