Hurricane weather module

Member for

19 years 10 months

Hi Dennis



You are right - a quick google gave no list of hurricne data over the years.



You may want to try:



www.wxresearch.com/outlook/2007hurout.pdf.



which does seem to have some information.



In hindsight it may well be:



www.wxresearch.com/outlook/2007/hurout.pdf.



Give it a try.



Best regards



Mike Testro



PS I have a personal interest in this because my family are flying back from Houston to Norwich International this afternoon.

Member for

18 years 6 months

Thanks Mike but the data i have been able to find is neither as specific nor as detailed as I would like - generally only annual totals. The best I have found are two charts for Morgan City and Sabine Pass.



I was hoping someone else may have some better data. Again thanks for the response.

Member for

19 years 10 months

Hi Dennis



I am sure that NASA at Houston have some sort of predictive software that they can share with you.



Otherwise look at the records of the last 5 years and work out the statistical probability of a hurricane hitting your project.



Set this in your calendar for your current project and then update when hurricanes actually happen.



Hardly a contingency in Hereford Herefordshire or Hamshire as My fair Lady would have it.



Best regards



Mike Testro.