Yes, in business there are many risk applications using the pseudo random number generator RAND() function. Fram a CPM standpoint, if you had the time you could perform a monte carlo analysis using RAND(). In fact time might not be that big an issue if you wanted to model only select activities.
For all the interested members in such concept (Risk Analysis Tools), Oracle has provide a much a mazing tool to re-plan and achieve a project goals in many meanings whether cost or time since the quality can be contended in project specifications, it called Oracle Primavera Risk Analysis, this tool can be used in conjunction with MSP, P3, P6, and can be loaded easily from officially Oracle website.
Mai
Member for
15 years 4 months
Member for15 years4 months
Submitted by Mike Lingard-Smith on Mon, 2010-10-11 14:23
I wish I have time to show you guys more. Anyway, this should give you an idea how to do this in EXCEL.
By the way, please check PERTMASTER and @RISK software. These two companies have add-on application for EXCEL, MS PROJECT,and P3 sebjected to RISK ANALYSIS
Member for
18 years 9 months
Member for18 years9 months
Submitted by Pranab Kumar Deb on Sun, 2009-04-19 07:34
I just join the planning planet by today and I saw the subject is really interested. Can some body send me the soft file of excel for risk analysis to my email : manikarori.rosky@conocophillips.com ?
appreciate with your support.
thanks,
ori
Member for
18 years 2 months
Member for18 years3 months
Submitted by andy sphicas on Tue, 2009-02-24 01:52
Hi Friend of PlanningPlanet, I would appreciate if you send me the excel file to ivanemejia@yahoo.com or ivanmejia70@hotmil.com. and I will come back with my comments about the way to improve it, if any.
Thanks in advance,
Ivan
Member for
18 years 9 months
Member for18 years10 months
Submitted by Chachrist Sris… on Tue, 2009-02-17 19:17
thanks for the inputs from those who like and dislike my simple RISK Analysis macro. I didnt plan to make it as an end product. My macro and the code should be viewed as a starter. It should show you how to make a simple simulation out of MS Excel and MS Project.
By the way, sorry I didnt write the manual, since I believe we all can figure out how it works.
iDecide is an award-winning software program for decision and risk analysis. With iDecide you can quickly build influence diagrams describing the risk or decision and then run Monte Carlo simulation. The result is a statistically accurate representation of the range and likelihood of all possible outcomes. In other words, iDecide gives you the power to handle risks and decisions like a professional.
If you really want to do proper Risk analysis where the formulae have been tested and the people who creted it actually know what they are doing try the following URL
Member for
16 years 6 monthsDear all, May i have copy
Dear all,
May i have copy too. please
Is it possible to use EXCEL as Risk Analysis Software on my id (maqeel2008@hotmail.com)
THANKS FOR HELP!!
REGARDS,
MAQEEL
Member for
15 years 1 monthYes, in business there are
Yes, in business there are many risk applications using the pseudo random number generator RAND() function. Fram a CPM standpoint, if you had the time you could perform a monte carlo analysis using RAND(). In fact time might not be that big an issue if you wanted to model only select activities.
Member for
15 years 8 monthsOracle Primavera Risk Analysis
Hi Dears:
For all the interested members in such concept (Risk Analysis Tools), Oracle has provide a much a mazing tool to re-plan and achieve a project goals in many meanings whether cost or time since the quality can be contended in project specifications, it called Oracle Primavera Risk Analysis, this tool can be used in conjunction with MSP, P3, P6, and can be loaded easily from officially Oracle website.
Mai
Member for
15 years 4 monthsRE: Excel as Risk Analysis Software
Hello,
Please can you send me a copy - always willing to learn and investigate defferent ways of Risk Analysis (mikelingardsmith@aol.com).
Kind Regards,
Mike
Member for
15 years 1 monthDear,Can you sned me
Dear,
Can you send me it,
agoudjilramzi@gmail.com
kindest Regards
Member for
15 years 9 monthsRE: EXCEL as Risk Analysis Software
Dear
I would like to have a copy!
Thank!
My e-mail address is garyjulia2005@yahoo.com.hk
Gary Lo
Member for
15 years 9 monthsRE: EXCEL as Risk Analysis Software
Dear
I would like to have a copy!
Thank!
My e-mail address is garyjulia2005@yahoo.com.hk
Gary Lo
Member for
16 years 3 monthsRE: EXCEL as Risk Analysis Software
Could I please have a copy too?
Email id thiru_abbas@yahoo.com
thanks in advance
Regards
abbas
Member for
16 years 7 monthsRE: EXCEL as Risk Analysis Software
Could I please have a copy too?
Email id mehmetegilmezer@hotmail.com
thanks in advance
Regards
mehmet
Member for
16 years 5 monthsRE: EXCEL as Risk Analysis Software
Dear Milind,
Could you please send me a copy to phamquocduy@gmail.com
Do Appreciate your reply.
Thanks
Member for
17 years 3 monthsRE: EXCEL as Risk Analysis Software
sir
please send me a copy of excel as Risk Analysis Software.
jvc_ce@yahoo.com
thank you very much
Member for
17 years 4 monthsRE: EXCEL as Risk Analysis Software
Hi Milind
Could you please send a copy
raosanjay65@hotmail.com
Member for
17 years 9 monthsRE: EXCEL as Risk Analysis Software
Dear Milind,
Pl send me a copy.
d_kole@rediffmail.com
Thanks,
Deb
Member for
16 years 10 monthsRE: EXCEL as Risk Analysis Software
Dear Milind,
Pls send me too.
Armanamail@gmail.com
Thanks
Member for
20 years 2 monthsRE: EXCEL as Risk Analysis Software
Guys please check your emails
i have send some Documents on Risk Management
Regard
Milind Pandhare
james.shimmon@magnoxsouthsites.com;
althaf314@gmail.com;
shibom@emirates.net.ae;
wei_junfeng@hotmail.com;
jonward77@hotmail.com;
Manish_k_pandey@yahoo.com
Member for
20 years 2 monthsRE: EXCEL as Risk Analysis Software
I have same sort of Excel Files regarding Risk Management
do contact me on
Mpandhare@laingorourke.ae
Milind123us@yahoo.co.in
Member for
19 years 1 monthRE: EXCEL as Risk Analysis Software
Could I please have a copy too?
Email id Manish_k_pandey@yahoo.com
thanks in advance
Regards
Manish
Member for
19 years 1 monthRE: EXCEL as Risk Analysis Software
Could I please have a copy too?
thanks in advance
Regards
Manish
Member for
18 years 9 monthsRE: EXCEL as Risk Analysis Software
hello all,
If anyone has a copy of the Excel file I would very much appreciate a copy of it.
jonward77@hotmail.com
Many thanks
Member for
16 years 11 monthsRE: EXCEL as Risk Analysis Software
Kindly email me a copy too, link below seem not to work.
Thanks & Cheers!
please go to
http://www.chachris.com/index_files/excel.htm
Member for
16 years 11 monthsRE: EXCEL as Risk Analysis Software
Is it too late to ask for a copy?
thanks in advance
wei_junfeng@hotmail.com
Member for
20 years 2 monthsRE: EXCEL as Risk Analysis Software
Dear PPers,
To all requesting copy of Chachrists risk analysis using MS Excel.
I copied here his Post # 13 for your convenience.
Just helping everyone.
Best regards,
R. Catalan
________________________________________________________
please goto
http://www.chachris.com/index_files/excel.htm
or
http://chachrist.googlepages.com/RiskAnalysis.pdf
I wish I have time to show you guys more. Anyway, this should give you an idea how to do this in EXCEL.
By the way, please check PERTMASTER and @RISK software. These two companies have add-on application for EXCEL, MS PROJECT,and P3 sebjected to RISK ANALYSIS
Member for
18 years 9 monthsRE: EXCEL as Risk Analysis Software
Hello I would also
like to have a copy of this macro
shibom@emirates.net.ae
Member for
16 years 10 monthsRE: EXCEL as Risk Analysis Software
Hi Guys send me a copy of excel risk analysis this plz to my ID
althaf314@gmail.com
Member for
18 years 9 monthsRE: EXCEL as Risk Analysis Software
I would like a copy as well from anybody
james.shimmon@magnoxsouthsites.com
cheers
Member for
16 years 7 monthsRE: EXCEL as Risk Analysis Software
Dear all,
I just join the planning planet by today and I saw the subject is really interested. Can some body send me the soft file of excel for risk analysis to my email : manikarori.rosky@conocophillips.com ?
appreciate with your support.
thanks,
ori
Member for
18 years 2 monthsRE: EXCEL as Risk Analysis Software
forgot to add my email
a.sphicas@cytanet.com.cy
could someone send me a copy as well?
thanks in advance
Member for
18 years 2 monthsRE: EXCEL as Risk Analysis Software
Could I please have a copy too? thanks
Andy Sphicas
Member for
22 years 2 monthsRE: EXCEL as Risk Analysis Software
Hi Friend of PlanningPlanet, I would appreciate if you send me the excel file to ivanemejia@yahoo.com or ivanmejia70@hotmil.com. and I will come back with my comments about the way to improve it, if any.
Thanks in advance,
Ivan
Member for
18 years 9 monthsRE: EXCEL as Risk Analysis Software
thanks for the inputs from those who like and dislike my simple RISK Analysis macro. I didnt plan to make it as an end product. My macro and the code should be viewed as a starter. It should show you how to make a simple simulation out of MS Excel and MS Project.
By the way, sorry I didnt write the manual, since I believe we all can figure out how it works.
Member for
17 yearsRE: EXCEL as Risk Analysis Software
Is it too late to ask for a copy?
thanks in advance
pasteur_78@yahoo.com
Member for
21 years 1 monthRE: EXCEL as Risk Analysis Software
can anybody send the subject file to me at maksabic@gmail.com
thanks in advance
AK
Member for
17 years 7 monthsRE: EXCEL as Risk Analysis Software
Hi Chachrist,
Id love to have a copy.
engr_ravelasco@yahoo.com
Happy Planning....
Member for
17 years 7 monthsRE: EXCEL as Risk Analysis Software
dear Chachrist
Thanks to send the file, i want to see how to make it
sorry my mail is l.messis@yahoo.fr
Member for
17 years 7 monthsRE: EXCEL as Risk Analysis Software
dear Chachrist
Thanks to send the file, i want to see how to make it
Member for
16 years 11 monthsRE: EXCEL as Risk Analysis Software
can somebody please send me a file of above subject
my email address is lestrell152@yahoo.com.ph
many thanks
and i just join the PP today (15NOV08)
Member for
24 years 9 monthsRE: EXCEL as Risk Analysis Software
Guys
I gave you the web address in my previous post
www.decisivetools.com
download a 30 day trial to see for yourself.
iDecide is an award-winning software program for decision and risk analysis. With iDecide you can quickly build influence diagrams describing the risk or decision and then run Monte Carlo simulation. The result is a statistically accurate representation of the range and likelihood of all possible outcomes. In other words, iDecide gives you the power to handle risks and decisions like a professional.
Raf
Member for
17 years 5 monthsRE: EXCEL as Risk Analysis Software
I would appretiate a copy of this software as well. Thank you very much. my email address is odilihenry@yahoo.com
Member for
17 years 2 monthsRE: EXCEL as Risk Analysis Software
Hi Chochrist,
Im interested. Is it possible for you to forward to me at engrnel_17@yahoo.com
Thanx..
Rnel
Member for
24 years 9 monthsRE: EXCEL as Risk Analysis Software
Folks
If you are so keen to write Risk Analysis using Excel, then there is a far better tool which cost about $USD 150.00
Go to www.decisivetools.com and look for i-decide
It has more maths than you have ever learnt
Raf
Member for
17 years 5 monthsRE: EXCEL as Risk Analysis Software
HI
cAN SOMEONE SEND ME A COPY AS WELL
THANKS
HENRY
Member for
24 years 9 monthsRE: EXCEL as Risk Analysis Software
Bipresh
If you really want to do proper Risk analysis where the formulae have been tested and the people who creted it actually know what they are doing try the following URL
http://www.projchallenge.com/solutions_presentations/Mark%20Swabey%20v%…
I have seen this product and reckon it beats all the rinky dink Excel macros that exist
Raf
Member for
18 years 6 monthsRE: EXCEL as Risk Analysis Software
can i get a copy of the excel templete for Monte- Carlo simulation at my id Bpaul@cbi.com
rgrds, BP
Member for
17 years 7 monthsRE: EXCEL as Risk Analysis Software
I would appretiate a copy of this software as well. Thank you very much.
Member for
17 years 7 monthsRE: EXCEL as Risk Analysis Software
my email add by the way is denmark_zb@yahoo.com. jejeje. thanks.
Member for
17 years 7 monthsRE: EXCEL as Risk Analysis Software
Hi all!
i would appreciate if someone send me a copy of the schedule risk analysis. Thank you!
regards,
denmark
Member for
17 years 7 monthsRE: EXCEL as Risk Analysis Software
Could you also please send me a copy of the risk analysis software.
contact_us43@yahoo.com.au
Much appreciated.
Member for
19 years 3 monthsRE: EXCEL as Risk Analysis Software
Hi all,
Pls copy me also at edris_md@yahoo.com
Member for
18 years 3 monthsRE: EXCEL as Risk Analysis Software
Hallo i would like to have a copy also THANK first!!! hehe
Email adds : chiteng83@hotmail.com
Member for
18 years 9 monthsRE: EXCEL as Risk Analysis Software
Could you email me a copy of the same at sah7818@hotmail.com please. Your efforts shall be appreciated.