Project Management Issues Discussion Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2018-07-23 14:39 Permalink you do not edit the finish you do not edit the finish date. If it is done then you mark it with an actual and the actual date it finished. Finish dates are calculated from the forward (early finsh) and Backward (late finish) scheduling passes that the program runs Member for 18 years 11 months Member for 18 years 11 months Submitted by Tom Boyle on Sun, 2018-07-22 14:19 Permalink What is the software? What is the software? Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2018-07-23 14:39 Permalink you do not edit the finish you do not edit the finish date. If it is done then you mark it with an actual and the actual date it finished. Finish dates are calculated from the forward (early finsh) and Backward (late finish) scheduling passes that the program runs
Member for 18 years 11 months Member for 18 years 11 months Submitted by Tom Boyle on Sun, 2018-07-22 14:19 Permalink What is the software? What is the software?
Member for
16 years 3 monthsyou do not edit the finish
you do not edit the finish date. If it is done then you mark it with an actual and the actual date it finished. Finish dates are calculated from the forward (early finsh) and Backward (late finish) scheduling passes that the program runs
Member for
18 years 11 monthsWhat is the software?
What is the software?