Hi Kannan, You are right. Negative SV only means that project is behind, as per the current schedule, on status or control date. It does not give any indication of the future work. For more on variances, you can look at https://www.pmbypm.com/basics-earned-value-analysis/
Member for
24 years 9 months
Member for24 years9 months
Submitted by Patrick Weaver on Sat, 2018-02-10 21:46
Member for
11 years 2 monthsHi Kannan, You are right.
Hi Kannan, You are right. Negative SV only means that project is behind, as per the current schedule, on status or control date. It does not give any indication of the future work. For more on variances, you can look at https://www.pmbypm.com/basics-earned-value-analysis/
Member for
24 years 9 monthsIf you are not doing enough
If you are not doing enough work there will eventually be a major issue -ve SV highlight this.
If you are not doing the right work there is a problem -ve Float highlights this.
You need both sets of information (and their trends) to really understand the situation on a project. See: https://mosaicprojects.com.au/Resources_Papers_117.html
Member for
16 years 3 monthsglad I could help
glad I could help
Member for
17 years 4 monthsagreed and thanks
agreed and thanks Zoltan..
Regards
Kannan
Member for
16 years 3 monthsnegative float yes ngeative
negative float yes
ngeative variance no because there can be float in the schedule that tyou are comparing against.