yes you can set it up to self populate then you cna set it up to import the activities into p6 from excel
notice it tied it to existing activities on the bakc end and well as kicking off the change order with a constraint date this actviivity should also tie to the begining of the project becasue every activity must have a predecessor and a successor
The schedule part got it. What about presenting it in Excel. Example
CategoryDeliverablesBudget Hours - AICO - BTotal Budgeted Hours - C = (A+B)Change Order - DTotal Budgeted -E = C + DCTRPFD80 80 80ICOFlare Dispersion Study 4040 40
So how would you present this to management not by schedule but in some other way. When it is approved by the Internal Stakeholders then you would add it to the schedule as you said. But what about the approval cycle and tracking it in a spreadsheet.
The schedule part got it. What about presenting it in Excel. Example
CategoryDeliverablesBudget Hours - AICO - BTotal Budgeted Hours - C = (A+B)Change Order - DTotal Budgeted -E = C + DCTRPFD80 80 80ICOFlare Dispersion Study 4040 40
So how would you present this to management not by schedule but in some other way. When it is approved by the Internal Stakeholders then you would add it to the schedule as you said. But what about the approval cycle and tracking it in a spreadsheet.
Regards
Jithin
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Tue, 2017-09-05 14:11
Many ways to do this. Add the activities in and creat a code called ICO internal change order and tag all of the added activities with this code. Do not add any cost assoicated with this change if yo uneed to track then track it in a spreadsheet and out these cost below the line this wil come of of your profit for the project or if you have any contingency.
Member for
16 years 3 monthsyes you can set it up to self
yes you can set it up to self populate then you cna set it up to import the activities into p6 from excel
notice it tied it to existing activities on the bakc end and well as kicking off the change order with a constraint date this actviivity should also tie to the begining of the project becasue every activity must have a predecessor and a successor
Member for
14 years 7 monthsGot it Zoltan. Thanks. Really
Got it Zoltan. Thanks. Really a good one indeed. Gives a good Idea with a Situation.
Thanks Again.
Regards
Jithin
Member for
16 years 3 monthssent
sent
Member for
14 years 7 monthsHi Zoltan, Thank you very
Hi Zoltan,
Thank you very much. Its kjithinnair@yahoo.co.in.
Thanks
Jithin
Member for
16 years 3 monthsI have an excel spreadsheet
I have an excel spreadsheet that I can share what is your email address.
Member for
14 years 7 monthsThanks Zoltan, The schedule
Thanks Zoltan,
The schedule part got it. What about presenting it in Excel. Example
CategoryDeliverablesBudget Hours - AICO - BTotal Budgeted Hours - C = (A+B)Change Order - DTotal Budgeted -E = C + DCTRPFD80 80 80ICOFlare Dispersion Study 4040 40
So how would you present this to management not by schedule but in some other way. When it is approved by the Internal Stakeholders then you would add it to the schedule as you said. But what about the approval cycle and tracking it in a spreadsheet.
Regards
Jithin
Member for
14 years 7 monthsThanks Zoltan, The schedule
Thanks Zoltan,
The schedule part got it. What about presenting it in Excel. Example
CategoryDeliverablesBudget Hours - AICO - BTotal Budgeted Hours - C = (A+B)Change Order - DTotal Budgeted -E = C + DCTRPFD80 80 80ICOFlare Dispersion Study 4040 40
So how would you present this to management not by schedule but in some other way. When it is approved by the Internal Stakeholders then you would add it to the schedule as you said. But what about the approval cycle and tracking it in a spreadsheet.
Regards
Jithin
Member for
16 years 3 monthsMany ways to do this. Add the
Many ways to do this. Add the activities in and creat a code called ICO internal change order and tag all of the added activities with this code. Do not add any cost assoicated with this change if yo uneed to track then track it in a spreadsheet and out these cost below the line this wil come of of your profit for the project or if you have any contingency.