Internal Change Order

Member for

16 years 3 months

yes you can set it up to self populate then you cna set it up to import the activities into p6 from excel 

notice it tied it to existing activities on the bakc end and well as kicking off the change order with a constraint date this actviivity should also tie to the begining of the project becasue every activity must have a predecessor and a successor 

Member for

14 years 7 months

Got it Zoltan. Thanks. Really a good one indeed. Gives a good Idea with a Situation.

 

Thanks Again.

 

Regards

Jithin

Member for

16 years 3 months

sent 

Member for

16 years 3 months

I have an excel spreadsheet that I can share what is your email address. 

Member for

14 years 7 months

Thanks Zoltan,

 

The schedule part got it. What about presenting it in Excel. Example

CategoryDeliverablesBudget Hours - AICO - BTotal Budgeted Hours - C = (A+B)Change Order - DTotal Budgeted -E = C + DCTRPFD80 80 80ICOFlare Dispersion Study 4040 40

So how would you present this to management not by schedule but in some other way. When it is approved by the Internal Stakeholders then you would add it to the schedule as you said. But what about the approval cycle and tracking it in a spreadsheet.

Regards

Jithin

 

Member for

14 years 7 months

Thanks Zoltan,

 

The schedule part got it. What about presenting it in Excel. Example

CategoryDeliverablesBudget Hours - AICO - BTotal Budgeted Hours - C = (A+B)Change Order - DTotal Budgeted -E = C + DCTRPFD80 80 80ICOFlare Dispersion Study 4040 40

So how would you present this to management not by schedule but in some other way. When it is approved by the Internal Stakeholders then you would add it to the schedule as you said. But what about the approval cycle and tracking it in a spreadsheet.

Regards

Jithin

 

Member for

16 years 3 months

Many ways to do this. Add the activities in and creat a code called ICO internal change order and tag all of the added activities with this code. Do not add any cost assoicated with this change if yo uneed to track then track it in a spreadsheet and out these cost below the line this wil come of of your profit for the project or if you have any contingency.