Project Management Issues Discussion Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2017-08-30 13:58 Permalink how about using manhours per how about using manhours per activity (direct labor) as your measuring stick ? you can use a blended rate for cost per manhour and it will multiply the manhours times the rate to give your your direct labor costs. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2017-08-30 13:58 Permalink how about using manhours per how about using manhours per activity (direct labor) as your measuring stick ? you can use a blended rate for cost per manhour and it will multiply the manhours times the rate to give your your direct labor costs.
Member for
16 years 3 monthshow about using manhours per
how about using manhours per activity (direct labor) as your measuring stick ? you can use a blended rate for cost per manhour and it will multiply the manhours times the rate to give your your direct labor costs.