ANY deviation from the plan must be explained in a narrative as to the reason for the change of the paln and the schedule must be revused to reflect the new plan. If not twhat use is the schedule. The schedule is meant to be a planning tool. How can you plan for any of the required material, equipment or manpower if the plan does not reflect current conditions ? Answer is that you can't therefore the schedule is flawed and needs to be revised to reflect the new conditions.
Member for
16 years 3 monthsthat is the best and only
that is the best and only solution
Member for
8 years 2 monthsHi thanks for your reply...I
Hi thanks for your reply...
I am working with the subbie planner to build a new programme which reflects the actual way the work is being carried out.
Member for
16 years 3 monthsANY deviation from the plan
ANY deviation from the plan must be explained in a narrative as to the reason for the change of the paln and the schedule must be revused to reflect the new plan. If not twhat use is the schedule. The schedule is meant to be a planning tool. How can you plan for any of the required material, equipment or manpower if the plan does not reflect current conditions ? Answer is that you can't therefore the schedule is flawed and needs to be revised to reflect the new conditions.