Works not reflecting accepted programme

Member for

16 years 3 months

that is the best and only solution 

Member for

8 years 2 months

Hi thanks for your reply...

I am working with the subbie planner to build a new programme which reflects the actual way the work is being carried out.

Member for

16 years 3 months

ANY deviation from the plan must be explained in a narrative as to the reason for the change of the paln and the schedule must be revused to reflect the new plan. If not twhat use is the schedule. The schedule is meant to be a planning tool. How can you plan for any of the required material, equipment or manpower if the plan does not reflect current conditions ? Answer is that you can't therefore the schedule is flawed and needs to be revised to reflect the new conditions.