The EAC calculation is based on the overall CPI, not the individual work package CPIs (for the simple reason the CPI on un-started work packages = 1 for the work package). The basic concept is that the best indicator for the performance of future work is the performance on work completed and all incomplete work needs to be scaled by the CPI.
The more correct term for EAC is 'Independent Estimate At Completion' - there are a range of formula in the standard, yours, the one proposed by Rafael and several others. the rules for IEAC is the means of calculation are determined first and then used consitently - you don't formula shop to get the best outcome. See: http://www.mosaicprojects.com.au/WhitePapers/WP1081_Earned_Value.pdf
Member for
21 years 8 months
Member for21 years8 months
Submitted by Rafael Davila on Thu, 2015-12-10 12:59
Different software might use different formulas so check with your software literature.
About - I calculate my EAC for each activity and sum it up to the WBS or project level, or do I use the calculated CPI at the project level and calculate it there?
I would expect both to yield the same value no matter what method your software uses. Your CPM software shall show EAC & CPI at all WBS levels down to activity level for any cost loaded schedule at a few mouse clicks.
Member for
24 years 9 monthsHi Jeff,To actually answer
Hi Jeff,
To actually answer the question you asked....
The EAC calculation is based on the overall CPI, not the individual work package CPIs (for the simple reason the CPI on un-started work packages = 1 for the work package). The basic concept is that the best indicator for the performance of future work is the performance on work completed and all incomplete work needs to be scaled by the CPI.
The more correct term for EAC is 'Independent Estimate At Completion' - there are a range of formula in the standard, yours, the one proposed by Rafael and several others. the rules for IEAC is the means of calculation are determined first and then used consitently - you don't formula shop to get the best outcome. See: http://www.mosaicprojects.com.au/WhitePapers/WP1081_Earned_Value.pdf
Member for
21 years 8 monthsI am not a fan of EVM nor of
I am not a fan of EVM nor of ES
http://www.earnedschedule.com/Docs/Forecasting%20Project%20Schedule%20C…
http://www.pmknowledgecenter.com/node/163
But maybe the correct formula is:
EAC=AC+ ((BAC-EV)/(CPI*SPI))
http://edward-designer.com/web/pmp-calculation-formulae/
Different software might use different formulas so check with your software literature.
About - I calculate my EAC for each activity and sum it up to the WBS or project level, or do I use the calculated CPI at the project level and calculate it there?
I would expect both to yield the same value no matter what method your software uses. Your CPM software shall show EAC & CPI at all WBS levels down to activity level for any cost loaded schedule at a few mouse clicks.
Good Luck