Project Management Issues Discussion Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2013-01-10 15:24 Permalink Hi Willem My advice is to Hi Willem My advice is to view the task exactly the same as you would when setting up a WBS for a new structure. List all the tasks on a spreadsheet and then put them into sequence. Add headings and sub headings with sequential numbering. Best regards Mike T. Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2013-01-10 15:24 Permalink Hi Willem My advice is to Hi Willem My advice is to view the task exactly the same as you would when setting up a WBS for a new structure. List all the tasks on a spreadsheet and then put them into sequence. Add headings and sub headings with sequential numbering. Best regards Mike T.
Member for
19 years 10 monthsHi Willem My advice is to
Hi Willem
My advice is to view the task exactly the same as you would when setting up a WBS for a new structure.
List all the tasks on a spreadsheet and then put them into sequence.
Add headings and sub headings with sequential numbering.
Best regards
Mike T.