Project Management Issues Discussion Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Thu, 2012-06-14 20:56 Permalink Why would you use the Why would you use the client's estimate of manhours instead of your own? Member for 15 years 11 months Member for 15 years 11 months Submitted by ronron martinez on Thu, 2012-06-14 16:43 Permalink Hi Mike,If I make manhour as Hi Mike, If I make manhour as per the quantity I end up supplying a lot of workers. Cause the client estimated Manhour for every quantity is over allocate? Do you have construction activities man-hours? Regard Ron Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Tue, 2012-06-05 21:15 Permalink Hi RonRon You can make a Hi RonRon You can make a direct extract of manhours from quantities using a simple percentage of Hours per Unit of measure. It doesn't matter how accurate it is just so long as you use the same ratio for each report. My motto is "Give then what they want" but not necessarily how they want it. Best regards Mike Testro Log in or register to post comments
Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Thu, 2012-06-14 20:56 Permalink Why would you use the Why would you use the client's estimate of manhours instead of your own?
Member for 15 years 11 months Member for 15 years 11 months Submitted by ronron martinez on Thu, 2012-06-14 16:43 Permalink Hi Mike,If I make manhour as Hi Mike, If I make manhour as per the quantity I end up supplying a lot of workers. Cause the client estimated Manhour for every quantity is over allocate? Do you have construction activities man-hours? Regard Ron
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Tue, 2012-06-05 21:15 Permalink Hi RonRon You can make a Hi RonRon You can make a direct extract of manhours from quantities using a simple percentage of Hours per Unit of measure. It doesn't matter how accurate it is just so long as you use the same ratio for each report. My motto is "Give then what they want" but not necessarily how they want it. Best regards Mike Testro
Member for
16 years 7 monthsWhy would you use the
Why would you use the client's estimate of manhours instead of your own?
Member for
15 years 11 monthsHi Mike,If I make manhour as
Hi Mike,
If I make manhour as per the quantity I end up supplying a lot of workers.
Cause the client estimated Manhour for every quantity is over allocate?
Do you have construction activities man-hours?
Regard
Ron
Member for
19 years 10 monthsHi RonRon You can make a
Hi RonRon
You can make a direct extract of manhours from quantities using a simple percentage of Hours per Unit of measure.
It doesn't matter how accurate it is just so long as you use the same ratio for each report.
My motto is "Give then what they want" but not necessarily how they want it.
Best regards
Mike Testro