Qty / Manhour

Member for

16 years 7 months

Why would you use the client's estimate of manhours instead of your own?

Member for

15 years 11 months

Hi Mike,

If I make manhour as per the quantity I end up supplying a lot of workers.

Cause the client estimated Manhour for every quantity is over allocate?

Do you have construction activities man-hours?

Regard

Ron

Member for

19 years 10 months

Hi RonRon

You can make a direct extract of manhours from quantities using a simple percentage of Hours per Unit of measure.

It doesn't matter how accurate it is just so long as you use the same ratio for each report.

My motto is "Give then what they want" but not necessarily how they want it.

Best regards

Mike Testro