E.O.T approval

Member for

19 years 10 months

Hi Ashraf

You have a number of problems here.

1.  Check you contract regarding client taking possession of the project - It may represent a de facto completion for the occupied section.

2.  Your GM refusal to finish the last 10% of the work is a dangerous tactic which may backfire.

3.  You do not have a Final Account situation yet because that will follow the TOC - in your interim or penultimate account include everything that you are owed.

My advice is to get the job finished and then enter into dispute mode.

Best regards

Mike Testro