1. Check you contract regarding client taking possession of the project - It may represent a de facto completion for the occupied section.
2. Your GM refusal to finish the last 10% of the work is a dangerous tactic which may backfire.
3. You do not have a Final Account situation yet because that will follow the TOC - in your interim or penultimate account include everything that you are owed.
My advice is to get the job finished and then enter into dispute mode.
Member for
19 years 10 monthsHi Ashraf You have a number
Hi Ashraf
You have a number of problems here.
1. Check you contract regarding client taking possession of the project - It may represent a de facto completion for the occupied section.
2. Your GM refusal to finish the last 10% of the work is a dangerous tactic which may backfire.
3. You do not have a Final Account situation yet because that will follow the TOC - in your interim or penultimate account include everything that you are owed.
My advice is to get the job finished and then enter into dispute mode.
Best regards
Mike Testro