Submission of allocated resources is already part of the Constractor's daily report. If is tiresome for the Contractor to reflect the actual resources in the schedule, he can request to do it in spreadsheets format (MS Excel) as it would be easy for him to link to other reports (daily report, resource histograms, etc.).
On typical contract scheduling requirements, the Client has the right to request the Contractor to show his resources in the submitted schedule..
Member for
20 years 2 monthsHi Moh, Submission of
Hi Moh,
Submission of allocated resources is already part of the Constractor's daily report. If is tiresome for the Contractor to reflect the actual resources in the schedule, he can request to do it in spreadsheets format (MS Excel) as it would be easy for him to link to other reports (daily report, resource histograms, etc.).
On typical contract scheduling requirements, the Client has the right to request the Contractor to show his resources in the submitted schedule..
Best regards,
R. Catalan