Labour calculation

Member for

19 years 10 months

Hi Shaik

It is a good idea to check the original date of a thread before taking time to prepare a detailed answer.

It may not be appreciated 4 years later.

Best regards

Mike Testro

Member for

18 years 3 months

Nornally it is 60Mhrs - 85 Mhrs with an AVG of - 75 Mhrs/Ton However depends upon the type of work (Raft,Wall,Column,Slab)& dia of rebar.

 

Regards,

Shaik

Member for

14 years 9 months

Can any one tell how many labour required for 01 metricton of reinforcement work.

Member for

18 years

Assumed a 5-day week for the inputs

The production rates:



75 mm screed : 3 sqm/hr

Render : 3 sqm/hr

Carpet tile : 3 sqm/hr

Vinyl sheet : 5 sqm/hr.



PS: There was a miscalculation w.r.t Vinyl sheetings.



Regards,


Member for

18 years 1 month

Can somebody of you who answered pls. also post the basis for coming to that result ? Helpful for members. rgds,

Member for

21 years 9 months

For the screed get it mechanicaly pumped and laid, should take a week and remember it needs to go off before you work on it whatever way its thrown in, and dry before you lay anything on it (that could take up to 7 weeks).

Member for

20 years 2 months

Thanks kutty for you help.



Other members comments would also be appreciated.

Member for

18 years

Hi James,



These are the rough figures.



A) 4.5 nos

B) 6 nos

C) Carpet tiles - 3.5 nos

Vinyl sheets - 6.3 nos

I am not having data for the matting. Trust this helps.



Regards,