Project Management Issues Discussion Member for 19 years 2 months Member for 19 years 2 months Submitted by ashraf alawady on Sat, 2007-09-29 08:39 Permalink RE: Monthly Reports you can do good presentation using power point to show:- breife discreption of the project. layout of the project project data sheet progress of the works delays and reasons of delays mitigation plan charts of the reources planned and actual ,cash floe planned and actual and over all progress planned and actual Member for 19 years 8 months Member for 19 years 8 months Submitted by Beatrice Nasui on Sun, 2007-09-16 09:31 Permalink RE: Monthly Reports Thank you for your interest. We just purchased Milestones Professional - this will solve the schedule reporting part. The other graphs we normally present in reports are for % progress, cashflow, manpower, curves for procurement etc. Member for 18 years 8 months Member for 18 years 8 months Submitted by Andrew Dick on Sat, 2007-09-15 20:36 Permalink RE: Monthly Reports Milestones Professional is a good graphical tool. Or there is Crysatl reports. It depends what you can get your hands on and what information you need to display. But there are many 3rd party tools availible. Andy Member for 22 years 4 months Member for 22 years 4 months Submitted by Shahzad Munawar on Fri, 2007-09-14 19:24 Permalink RE: Monthly Reports You may produce your Monthly Report in a presentable way by using PDF software namely Adobe Acrobat 7.0 Standard. Log in or register to post comments
Member for 19 years 2 months Member for 19 years 2 months Submitted by ashraf alawady on Sat, 2007-09-29 08:39 Permalink RE: Monthly Reports you can do good presentation using power point to show:- breife discreption of the project. layout of the project project data sheet progress of the works delays and reasons of delays mitigation plan charts of the reources planned and actual ,cash floe planned and actual and over all progress planned and actual
Member for 19 years 8 months Member for 19 years 8 months Submitted by Beatrice Nasui on Sun, 2007-09-16 09:31 Permalink RE: Monthly Reports Thank you for your interest. We just purchased Milestones Professional - this will solve the schedule reporting part. The other graphs we normally present in reports are for % progress, cashflow, manpower, curves for procurement etc.
Member for 18 years 8 months Member for 18 years 8 months Submitted by Andrew Dick on Sat, 2007-09-15 20:36 Permalink RE: Monthly Reports Milestones Professional is a good graphical tool. Or there is Crysatl reports. It depends what you can get your hands on and what information you need to display. But there are many 3rd party tools availible. Andy
Member for 22 years 4 months Member for 22 years 4 months Submitted by Shahzad Munawar on Fri, 2007-09-14 19:24 Permalink RE: Monthly Reports You may produce your Monthly Report in a presentable way by using PDF software namely Adobe Acrobat 7.0 Standard.
Member for
19 years 2 monthsRE: Monthly Reports
you can do good presentation using power point to show:-
breife discreption of the project.
layout of the project
project data sheet
progress of the works
delays and reasons of delays
mitigation plan
charts of the reources planned and actual ,cash floe planned and actual and over all progress planned and actual
Member for
19 years 8 monthsRE: Monthly Reports
Thank you for your interest.
We just purchased Milestones Professional - this will solve the schedule reporting part. The other graphs we normally present in reports are for % progress, cashflow, manpower, curves for procurement etc.
Member for
18 years 8 monthsRE: Monthly Reports
Milestones Professional is a good graphical tool. Or there is Crysatl reports.
It depends what you can get your hands on and what information you need to display.
But there are many 3rd party tools availible.
Andy
Member for
22 years 4 monthsRE: Monthly Reports
You may produce your Monthly Report in a presentable way by using PDF software namely Adobe Acrobat 7.0 Standard.