Acceleration Cost

Member for

20 years 4 months

This has to be approached seperately. Show the design impact in the existing schedule, then roll the file and show how acceleration will get you back to your original completion date (assuming it’s possible).



So true to document delays as they happen.

Member for

21 years 5 months

Dear Basheer,



If i understand right, then u have to prepare an EOT claim programme to justify that the project shall be extended beyond the required date.



If the client has instructed you that he needs acceleration then u need to devise an acceleration plan and show it as a comparision to the EOT claims programme to indicate the acceleration. Further more u need to substantiate that actual acceleration cost is being incurred by maintaining accurate and up to date records such as daily reports, productivity calculations, introduction of extra man-power, equipment, comparision of original planned histograms to the accelerated planned and actual histograms etc.



I donot believe that once the client has issued the acceleration instruction he will grant an EOT.



Regards

Member for

19 years 2 months

Dear all

as per the condition of contract , No acceleration to be carried out without clear instruction fromthe client/Engineer.



The contractor has to stick to do the works as per the production rates mentioned in the original approved programme.



if there is no delays from the contractor side, no body can foce him to submit any other programme without clear instruction .



if the client issued an instruction to accelerate the works

by adding more resources and extending the working hours and working in fridays and other public holidays then, the contractor is clearly entitled for reasonable acceleration cost .

Member for

19 years 7 months

Hi Mohamed,



U’ve to separate between the 2 issues that u are facing here.

1- The EOT due to the changes in design.

2- The acceleration that the client want in the whole or part of the works has to be reimbursed (u’ve to read the contract to know whether u’ve priorities in the project or not in order to know whether u are obliged to complete certain part of the project before another).


Member for

18 years 6 months

Hi Basheer,



I have similar type of experience as we were delayed by the client due to design change, material shortage, acess release.We were first asked to provide a revised plan then we were asked to submit an accelaration plan. The issue dragged for almost eight months and was only resolved with the intervention of the honor.



The lesson learnt for me was that, success for Contractor lies in submitting theor calims early and regularly and sicking their ground for the cost of accelaration as you cannot sustain the work if profitability is not there. As far as you keep on submitting the claims one day or another it will be resolved and you will get your money.



Use the unit rates in the Contract and build your claim and try first to convince your management then they shall take on with the client.





Hope this may be of some help to you,



Regards,





Ashraf

Member for

21 years 7 months

I am mot that lucky Mr.Anoon Iimos

Member for

19 years 1 month

i suggest you keep cool!, go to the middle of the Causeway, breath the air and drink tea!