Actual cost and Earned value cost

Member for

13 years 9 months

Kannan,

The Actual Cost= Invoices Paid+Invoices Acrrued - Disallowed Costs...

EV= % of the Total budgeted cost...

So, they both are diffrent values and can't be same.

 

Thank you,

 

HASAN

Member for

15 years 11 months

Anning,

It works....

 

[[wysiwyg_imageupload:1064:]]

Member for

13 years 9 months

 

That would be helpful to know there is a shorter way to have EV cost similar to actual cost.

As we all know,  EV cost is based on %performance complete x budget cost. Actual cost is calculated on %complete x budget, BUT in this case, %complete maybe based on units, physical or duration, depending on settings of the duration type for each activity. The % performance complete is not necessarily the same as the %complete based on units, physical or duration; hence the difference in values for EV and actual costs.

Raymund, Tools -> update progress may not work in the objective. Try it, as we had, and it didnt yield the same cost for EV and actual cost.

 

 

Member for

15 years 11 months

Kannan,

Use Tool... Update Progress.

Member for

14 years 5 months

Kannan,

For me, you cannot make the same result between Earned and Actual Value in P6 unless otherwise you formulate it.

 

Thanks.