Print Preview Problem P6

Member for

16 years 3 months

they only way to get the bars to EVER display correct is to perform the backward pass which is by scheduling the project.

Also remember importing and MSP project is not exact even the alogrithm for the calculatons is different. 

The way that it uses calendars is different and the way it schedules relations can be different

Best bet is ALWASY re-schedule the project 

Member for

14 years 4 months

The issue was that the correct answer to the problem had not been supplied, and this thread appears in google searches.

If a schedule has never been rescheduled via F9, it will not display the Gantt Chart when printing. This is true for both new P6 schedules or for MSP imports. You can test this by creating a new P6 schedule, add in a few activities but do not schedule (F9) it, and then print preview.

While it is a simple solution to just F9 an MSP import to get the Gantt Chart to display, I am always very cautious in F9'ing any schedule that I didn't create as I do not know if the logic is sound. MSP files I receive often have particularly bad or incomplete logic...

Member for

16 years 3 months

So Matt I do not see an issue here you schedule it prints done

Member for

14 years 4 months

I know this is a very old thread, and I assume that everyone that has experienced this has resolved it by now, but I wanted to post the solution to this as it comes up in google searches.

An MSP import will not display the Gantt chart on import until the project has been scheduled (F9'd). Once you have F9'd the Gantt chart will once again print.

Member for

16 years 3 months

change setup default printer to Adobe pdf in the windows settings

Member for

7 years 4 months

I am currently having this exact issue. Did anyone resolve this?

 

Thanks,

 

David

Member for

14 years 7 months

Make sure your PS and PF are not greyed out. If they did, use custom dates. To verify this, go to page setup then options. I had the same issue and for some reason, PF was greyed out when I imported from XML file. 

Member for

14 years 1 month

Amit

I have already selected to show the Gantt Chart within the Activities Window before I then click on Print Preview.

Weird!!

Thanks

Rhys

Member for

14 years 11 months

Hi Rhys,

Gantt Chart view should also be enabled in your layout before you can use print preview. Enable gantt chart in your layout and then try checking your print preview.

Regards

Amit

Check out my blog on Primavera at http://www.primaverablog.in

Member for

14 years 1 month

Rajesh

 

I have made sure all this is in place the Planned start date and data date match and all the Print Preview Setting are all correct.

 

under the Timescale Start I have PS (early project start) & Timescale Finish is PF (Latest Project finish)

 

It still doesnt show the Gantt Chart only the Activities are listed.

 

I don't know if it is something to do with it being an Import from MSP as an XML as If I make one in P6 and then run a print preview it seems to work.

I dont see why that would cause the problem though. I really need this to work as clients within my company send me MSP files which I Import into P6 and then I normally PDF the Project Plan showing all activities and Gantt Chart.

 

Thanks

 

Rhys

Member for

19 years 1 month

Rhys,

Check the following in your project -

1. Project Details window > 'Dates' tab> see if Planned start date and data date are accurate.

2. Print preview > Page Setup > under 'Print' see if check box for 'Gantt Chart' is checked

3. Print preview > Page Setup > check of 'Timescaled Start' and 'Timescaled Finish' are set to 'PS - Project Start' and 'PF - Project Finish'

Let me know if it works.

Thanks,

Rajesh