Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2018-06-21 14:10 Permalink 1st you need to turn your 1st you need to turn your times on edit user prefernces Dates tab under time select 12 hour show minutes 2nd set the project start time to 8:00 am or the earliest starting times of of all of your calendars say 8:00 am 3rd then you need to set your data date time to 8:00 am or the earliest staring times of all of your calendars. 4th all start minestones should be set to 8:00 am or the earliest starting times of of all of your calendars 5th all finish milestones times should be set to 5:0 pm or the latest finishing times of all your calendars 6th the project must finish by date should be set to 5:0 pm or the latest finishing times of all your calendars 7th all actual start dates should be set to 8:00 am or the earliest starting of of all of your calendars 8th all actual finish date should be set to 5:00 pm or the latest finishing times of all of your calendars 9th edit user prefernces time units tab under durations format make sure that decimals are set to 2 places. 10th look at al of your originial durations and remaing durations and make sure that they are whole numbers 11th press F9 and change the data date time to 8:00 am or the earliest starting times of of all of your calendars done Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2018-06-21 09:05 Permalink Virendra,Open the appropriate Virendra, Open the appropriate calendar, click on Detailes work/hours per day, click on specific 30mn periods to switch from off to on by default, the working day spans from 8:00 am to 12:00 am and from 1:00 pm to 5:00 pm Member for 11 years 1 month Member for 11 years 1 month Submitted by vi*****@g***** on Thu, 2018-06-21 05:07 Permalink Good Morning,Can anyone help Good Morning, Can anyone help me to find out and explain me, how to change the start time i.e. 07.00AM and breaktime 1 hours in P6. Thanks in advance VKD +7 701035 4732 / +91 78694 65514 Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Wed, 2011-03-09 00:06 Permalink http://primavera.zxlm.cn/kb/p http://primavera.zxlm.cn/kb/prim71974 http://www.planningplanet.com/forums/primavera-version-pm5-pm6/421289/strange-problem-must-finish-date-p6 Weird, indeed. Member for 15 years 8 months Member for 15 years 8 months Submitted by Peter Anderson on Tue, 2011-03-08 23:22 Permalink Thanks - though in this Thanks - though in this instance I have not imported or exported anything to Excel. Any other solutions? Member for 14 years 8 months Member for 14 years 8 months Submitted by svb130360 on Tue, 2011-03-08 11:36 Permalink This will happen only when This will happen only when you are importing from Excel. In such case, please incorporate Calendar timing along with your dates. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2018-06-21 14:10 Permalink 1st you need to turn your 1st you need to turn your times on edit user prefernces Dates tab under time select 12 hour show minutes 2nd set the project start time to 8:00 am or the earliest starting times of of all of your calendars say 8:00 am 3rd then you need to set your data date time to 8:00 am or the earliest staring times of all of your calendars. 4th all start minestones should be set to 8:00 am or the earliest starting times of of all of your calendars 5th all finish milestones times should be set to 5:0 pm or the latest finishing times of all your calendars 6th the project must finish by date should be set to 5:0 pm or the latest finishing times of all your calendars 7th all actual start dates should be set to 8:00 am or the earliest starting of of all of your calendars 8th all actual finish date should be set to 5:00 pm or the latest finishing times of all of your calendars 9th edit user prefernces time units tab under durations format make sure that decimals are set to 2 places. 10th look at al of your originial durations and remaing durations and make sure that they are whole numbers 11th press F9 and change the data date time to 8:00 am or the earliest starting times of of all of your calendars done
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2018-06-21 09:05 Permalink Virendra,Open the appropriate Virendra, Open the appropriate calendar, click on Detailes work/hours per day, click on specific 30mn periods to switch from off to on by default, the working day spans from 8:00 am to 12:00 am and from 1:00 pm to 5:00 pm
Member for 11 years 1 month Member for 11 years 1 month Submitted by vi*****@g***** on Thu, 2018-06-21 05:07 Permalink Good Morning,Can anyone help Good Morning, Can anyone help me to find out and explain me, how to change the start time i.e. 07.00AM and breaktime 1 hours in P6. Thanks in advance VKD +7 701035 4732 / +91 78694 65514
Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Wed, 2011-03-09 00:06 Permalink http://primavera.zxlm.cn/kb/p http://primavera.zxlm.cn/kb/prim71974 http://www.planningplanet.com/forums/primavera-version-pm5-pm6/421289/strange-problem-must-finish-date-p6 Weird, indeed.
Member for 15 years 8 months Member for 15 years 8 months Submitted by Peter Anderson on Tue, 2011-03-08 23:22 Permalink Thanks - though in this Thanks - though in this instance I have not imported or exported anything to Excel. Any other solutions?
Member for 14 years 8 months Member for 14 years 8 months Submitted by svb130360 on Tue, 2011-03-08 11:36 Permalink This will happen only when This will happen only when you are importing from Excel. In such case, please incorporate Calendar timing along with your dates.
Member for
16 years 3 months1st you need to turn your
1st you need to turn your times on edit user prefernces Dates tab under time select 12 hour show minutes
2nd set the project start time to 8:00 am or the earliest starting times of of all of your calendars say 8:00 am
3rd then you need to set your data date time to 8:00 am or the earliest staring times of all of your calendars.
4th all start minestones should be set to 8:00 am or the earliest starting times of of all of your calendars
5th all finish milestones times should be set to 5:0 pm or the latest finishing times of all your calendars
6th the project must finish by date should be set to 5:0 pm or the latest finishing times of all your calendars
7th all actual start dates should be set to 8:00 am or the earliest starting of of all of your calendars
8th all actual finish date should be set to 5:00 pm or the latest finishing times of all of your calendars
9th edit user prefernces time units tab under durations format make sure that decimals are set to 2 places.
10th look at al of your originial durations and remaing durations and make sure that they are whole numbers
11th press F9 and change the data date time to 8:00 am or the earliest starting times of of all of your calendars
done
Member for
22 years 9 monthsVirendra,Open the appropriate
Virendra,
Open the appropriate calendar, click on Detailes work/hours per day,
click on specific 30mn periods to switch from off to on
by default, the working day spans from 8:00 am to 12:00 am and from 1:00 pm to 5:00 pm
Member for
11 years 1 monthGood Morning,Can anyone help
Good Morning,
Can anyone help me to find out and explain me, how to change the start time i.e. 07.00AM and breaktime 1 hours in P6.
Thanks in advance
VKD +7 701035 4732 / +91 78694 65514
Member for
21 years 8 monthshttp://primavera.zxlm.cn/kb/p
http://primavera.zxlm.cn/kb/prim71974
http://www.planningplanet.com/forums/primavera-version-pm5-pm6/421289/strange-problem-must-finish-date-p6
Weird, indeed.
Member for
15 years 8 monthsThanks - though in this
Thanks - though in this instance I have not imported or exported anything to Excel.
Any other solutions?
Member for
14 years 8 monthsThis will happen only when
This will happen only when you are importing from Excel. In such case, please incorporate Calendar timing along with your dates.