Earned Value - At Completion values with Current dates

Member for

16 years 3 months

the key wording here is the 1st word Budget of the 1st 2 options the 3rd option is AT completion which could be more or less than the budget.

Member for

19 years 6 months

1) Budgeted value with planned dates

PV = budget value x time spread or budget value x cost spread

 2) Budgeted value with current dates

PV = budget x current elapsed duration / total duration with expected completion

3) At completion value with current dates

PV = EAC x current elapsed dur / total dur with expected completion