Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2019-10-08 13:57 Permalink the key wording here is the the key wording here is the 1st word Budget of the 1st 2 options the 3rd option is AT completion which could be more or less than the budget. Member for 19 years 6 months Member for 19 years 6 months Submitted by Dinesh Kumar on Tue, 2019-10-08 10:56 Permalink 1) Budgeted value with 1) Budgeted value with planned dates PV = budget value x time spread or budget value x cost spread 2) Budgeted value with current dates PV = budget x current elapsed duration / total duration with expected completion 3) At completion value with current dates PV = EAC x current elapsed dur / total dur with expected completion Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2019-10-08 13:57 Permalink the key wording here is the the key wording here is the 1st word Budget of the 1st 2 options the 3rd option is AT completion which could be more or less than the budget.
Member for 19 years 6 months Member for 19 years 6 months Submitted by Dinesh Kumar on Tue, 2019-10-08 10:56 Permalink 1) Budgeted value with 1) Budgeted value with planned dates PV = budget value x time spread or budget value x cost spread 2) Budgeted value with current dates PV = budget x current elapsed duration / total duration with expected completion 3) At completion value with current dates PV = EAC x current elapsed dur / total dur with expected completion
Member for
16 years 3 monthsthe key wording here is the
the key wording here is the 1st word Budget of the 1st 2 options the 3rd option is AT completion which could be more or less than the budget.
Member for
19 years 6 months1) Budgeted value with
1) Budgeted value with planned dates
PV = budget value x time spread or budget value x cost spread
2) Budgeted value with current dates
PV = budget x current elapsed duration / total duration with expected completion
3) At completion value with current dates
PV = EAC x current elapsed dur / total dur with expected completion