Impact Of Calc Start-To-Start Lag From Actual Start

Member for

16 years 3 months

Khuong has the correct explaination 

Member for

18 years 5 months

A lot depends on the project status and also on the agressiveness of the Planning Engr.



I would prefer to have this calculated using Early Start, as this will give more conservative Schedule but again this will also lead to delay in start of successor.



Choice is yours!!