A lot depends on the project status and also on the agressiveness of the Planning Engr.
I would prefer to have this calculated using Early Start, as this will give more conservative Schedule but again this will also lead to delay in start of successor.
Member for
16 years 3 monthsKhuong has the correct
Khuong has the correct explaination
Member for
15 years 8 monthsHi there,I wrote an article
Hi there,
I wrote an article to explain these options.
Kindly read it here https://doduykhuong.com/2020/01/26/primavera-p6-schedule-options-calculate-start-to-start-lag-from/
Regards,
Khuong
Member for
21 years 1 monthRE: Impact Of Calc Start-To-Start Lag From Actual Start
Gentleman,
Can you expalin the question and answer as well please.
thanks
AK
Member for
18 years 5 monthsRE: Impact Of Calc Start-To-Start Lag From Actual Start
A lot depends on the project status and also on the agressiveness of the Planning Engr.
I would prefer to have this calculated using Early Start, as this will give more conservative Schedule but again this will also lead to delay in start of successor.
Choice is yours!!