You have made a user baseline. You must have selected current project as project baseline in Assign Baseline dialouge box.
You should go to Bars in gantt chart . There you mark the check-box of primary baseline bar & in timescale column next to bar column you select primary baseline.
Hope this should help.
If not, pls send me screenshots of how you are maintaining & assigning baselines to my mailid.
If you chose a current project as a baseline then your baseline bars will move when you change the logic. You have to save your current project as new file and assigned that as a primary baseline. Any changes to your current project will not affect your primary baseline.
To save current project as baseline:
1) Select Project -> Maintain baseline
2) Click Add and Tick “Save a copy of current project as a new Baseline” and click Ok
3) Select Project -> Assign baseline
4) On User Baseline under Primary -> Select the new save baseline from the dropdown box and not the current Project.
You should have a fixed primary baseline.
Hope this help,
Rodel
Member for
19 years 11 months
Member for19 years11 months
Submitted by Donovan Govender on Wed, 2007-10-17 00:25
Member for
18 yearsRE: P5 Why does my baseline bar move when i update
Hi, this is Nikhil.
You have made a user baseline. You must have selected current project as project baseline in Assign Baseline dialouge box.
You should go to Bars in gantt chart . There you mark the check-box of primary baseline bar & in timescale column next to bar column you select primary baseline.
Hope this should help.
If not, pls send me screenshots of how you are maintaining & assigning baselines to my mailid.
nmenkudale@gmail.com
Regards
Nikhil
Member for
18 years 1 monthRE: P5 Why does my baseline bar move when i update
Hi.
And be sure that you show the correct bar in Gantt chart.
Sometime we assign baseline to project-baseline but show out Primary-baseline in Gantt chart.
Thanks
Member for
19 years 11 monthsRE: P5 Why does my baseline bar move when i update
Thanks guys, I did not have my baseline in the primary box- it was still current
Regards
Donovan
Member for
19 yearsRE: P5 Why does my baseline bar move when i update
Donovan,
If you chose a current project as a baseline then your baseline bars will move when you change the logic. You have to save your current project as new file and assigned that as a primary baseline. Any changes to your current project will not affect your primary baseline.
To save current project as baseline:
1) Select Project -> Maintain baseline
2) Click Add and Tick “Save a copy of current project as a new Baseline” and click Ok
3) Select Project -> Assign baseline
4) On User Baseline under Primary -> Select the new save baseline from the dropdown box and not the current Project.
You should have a fixed primary baseline.
Hope this help,
Rodel
Member for
19 years 11 monthsRE: P5 Why does my baseline bar move when i update
Hi Rodel,
When I created the baseline, i chose project, maintain baseline,selected the current project i was in,clicked add.
now when I open maintain diologue box it shows the project name and baseline name,
under basline name- it shows the baseline
in baseline type - it shows "none"
data date -24 sep 07
in last update date- it shows 9 Oct 07
now I dont if 9 oct07 should be there,maybe i did something to cause it to go to 9 oct 07 i have updated my schedule on 5 oct 07, and now on 12 oct07.
what have done wrong or did I not do
Regards
Donovan
Member for
19 yearsRE: P5 Why does my baseline bar move when i update
Donovan,
Are you using Assigned Baseline or a current project as a baseline?
HTH,
Rodel