Export to MSP

Member for

18 years 6 months

Then it’s a good thing my company are cheap enough to still be using 2002!

Member for

24 years 6 months

And don’t forget if you load MSP 2007 you will not be able to import or export any MSP files!



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

Member for

20 years 7 months

Oliver,



The answer is no I’m afraid.



If you export to MSP you’ll likely to lose quite a lot more that ’just’ LOE tasks. For instance: secondary constraints, the difference between start and finish milestones, multiple dependencies between activities (SS+FF), your status date, reschedule of the remaining work, multiple resource assignments to the same activity.



Furthermore Primavera is a lot more picky in its start and finish dates. For instance, MSP sometimes starts an activity on Friday 17:00, in P5 this will be Monday 9:00. So it is likely your schedule will be slightly different too. Especially with a schedule in progress!



H.T.H.



Niek.