In planning terms a S Curve usually shows progress over time. The curve is usually shaped like a S because intially progress is slow, then ramps up in the middle of the project before levelling off at the end.
All projects though do not follow the S curve format with some being more front loaded while others are back loaded; or even middle laoded (bell shaped curve)..
Member for
18 years 6 monthsRE: What is an S-Curve?
Thank you
Member for
19 years 4 monthsRE: What is an S-Curve?
Hi Chris,
In planning terms a S Curve usually shows progress over time. The curve is usually shaped like a S because intially progress is slow, then ramps up in the middle of the project before levelling off at the end.
All projects though do not follow the S curve format with some being more front loaded while others are back loaded; or even middle laoded (bell shaped curve)..
keep planning,
Kevin.