Thanks for your replies guys.



I think you’re both right, I certainly cannot find a way to level materials, so I’ll convert all the material limits into units and try to do it that way.



Many thanks

Chris

Member for

24 years 9 months

Unfortunately Primavera does not level materials.

Member for

21 years

hi

I think it is better to use "units & Prices" in resource view. just becareful that you should fill two options as follow:

1) max/units time: the available amount of water in each period.

2) price/unit = 1