Oracle Primavera - PM6 Member for 19 years 4 months Member for 19 years 4 months Submitted by Kevin Matthews on Fri, 2007-08-24 04:25 Permalink RE: Copying Codes in P5 Thanks again Dieter, Keep planning, Kevin. Member for 18 years 9 months Member for 18 years 10 months Submitted by Dieter Wambach on Wed, 2007-08-15 06:56 Permalink RE: Copying Codes in P5 Hi Kevin In P5 its much easier to assign codes than in 3.1. On the right side of the screen there are some icons, Number 4 from below is "Assign Activity Codes". Now you can select groups of activities and assign codes to them - or remove codes from them. "Fill Down" works very similiar to P3 3.1. Regards Dieter Log in or register to post comments
Member for 19 years 4 months Member for 19 years 4 months Submitted by Kevin Matthews on Fri, 2007-08-24 04:25 Permalink RE: Copying Codes in P5 Thanks again Dieter, Keep planning, Kevin.
Member for 18 years 9 months Member for 18 years 10 months Submitted by Dieter Wambach on Wed, 2007-08-15 06:56 Permalink RE: Copying Codes in P5 Hi Kevin In P5 its much easier to assign codes than in 3.1. On the right side of the screen there are some icons, Number 4 from below is "Assign Activity Codes". Now you can select groups of activities and assign codes to them - or remove codes from them. "Fill Down" works very similiar to P3 3.1. Regards Dieter
Member for
19 years 4 monthsRE: Copying Codes in P5
Thanks again Dieter,
Keep planning,
Kevin.
Member for
18 years 9 monthsRE: Copying Codes in P5
Hi Kevin
In P5 its much easier to assign codes than in 3.1.
On the right side of the screen there are some icons, Number 4 from below is "Assign Activity Codes". Now you can select groups of activities and assign codes to them - or remove codes from them.
"Fill Down" works very similiar to P3 3.1.
Regards
Dieter